. 24/7 Space News .
WATER WORLD
Niger speeds up efforts to build first hydroelectric dam
By Boureima HAMA
Dessa, Niger (AFP) Sept 24, 2021

In a busy construction site, soldiers armed with guns watch over workers as Niger speeds up efforts to build its first hydroelectric dam to stem power shortages and food crises, despite security concerns in a restive area.

Long in the works and long delayed, the Kandadji dam project aims to free the world's poorest nation of its energy dependence on neighbouring Nigeria and boost agricultural production to try and end chronic food insecurity.

At the bottom of an enormous crater dug out with dynamite, excavators smash blocks of granite.

"Here, a major branch of the river has been drained -- it's here that the dam wall will be erected," says a Chinese engineer, his helmet tightly fixed.

"We are making good progress!"

In this huge Sahel state which is two-thirds desert, plans for the dam on the Niger river in the country's west have long been afoot.

In the 1970s, after a severe famine, General-President Seyni Koutche (1974-1987) nurtured the idea of providing Niger with a large-scale hydroelectric dam.

All the heads of state who succeeded him made this infrastructure "a priority", but the dam never saw the light of day.

A first stone was laid in 2008 under the presidency of Mamadou Tandja, but the political instability of the years that followed put a halt to the project.

Initially entrusted to the Russian firm Zarubezhvodstroy, the work has since been given to the Chinese company Gezhouba Group.

Already postponed many times, first to 2016 and then to 2023, the date to fill the reservoir behind the dam is set at 2025 according to the authorities, after further delays due to the Covid-19 pandemic.

- Massive scheme -

According to the UN's Human Development Index, Niger is the poorest nation on Earth, ranking 189th out of 189.

This mammoth project of 740 billion CFA francs (1.1 billion euros / $1.3 billion) is co-financed by the World Bank, African Development Bank (AfDB), Islamic Development Bank and French Development Agency.

With its 28-metre-high dam wall, it will have a retention capacity of 1.5 billion cubic meters, or 600,000 Olympic pools.

The project also entails the displacement of 50,000 people, of whom 7,000 have already been relocated, according to the Kandadji Dam Agency.

Now, "all the obstacles have been lifted (...) all the funding problems have been resolved. In a few months you will see the project taking shape," said Niger's President Mohamed Bazoum, who visited in mid-September.

Located some 180 kilometres (112 miles) upstream from the capital Niamey, in the heart of the "three borders" area that also includes Burkina Faso and Mali, the project has thus far been spared from the jihadist attacks that regularly plague the volatile region.

But Bazoum promised to "increase the number of soldiers to enable" the site to run day and night.

- 'Large-scale energy needs' -

An environmental impact study was completed in 2018 by the AfDB.

While other options such as solar or wind power were also evaluated, the report concluded that alternative energies could "not meet large-scale energy needs."

"The only solution that can solve the recurring problem of food insecurity in Niger is the Kandadji dam because there will be 45,000 hectares (111,200 acres) of land that will be developed to improve production," says Ousmane Danbadji, head of the Network of journalists for water and sanitation (Rejea) and an expert on the matter.

The dam agency forecasts that 400,000 more tonnes of rice, corn and vegetables will be produced each year in a country where 80 percent of the population lives off traditional agriculture, dependent on rains.

A 130-megawatt power station is due to be built in Kandadji, aiming to generate enough electricity annually to enable Niger to free itself from its energy dependence on neighbouring Nigeria.

Barely 15 percent of more than 20 million Nigeriens have electricity, according to the Nigelec electricity company.


Related Links
Water News - Science, Technology and Politics


Thanks for being there;
We need your help. The SpaceDaily news network continues to grow but revenues have never been harder to maintain.

With the rise of Ad Blockers, and Facebook - our traditional revenue sources via quality network advertising continues to decline. And unlike so many other news sites, we don't have a paywall - with those annoying usernames and passwords.

Our news coverage takes time and effort to publish 365 days a year.

If you find our news sites informative and useful then please consider becoming a regular supporter or for now make a one off contribution.
SpaceDaily Monthly Supporter
$5+ Billed Monthly


paypal only
SpaceDaily Contributor
$5 Billed Once


credit card or paypal


WATER WORLD
Egypt, Sudan back resumed Nile dam talks as UN urges deal
Cairo (AFP) Sept 16, 2021
Egypt and Sudan have expressed readiness to resume talks with Ethiopia on its controversial Nile dam after the UN Security Council urged the three governments to swiftly reach a binding deal. Set to be Africa's largest hydroelectric project when completed, the Grand Ethiopian Renaissance Dam (GERD) has sparked an almost decade-long diplomatic stand-off between Ethiopia and downstream nations Egypt and Sudan. On Wednesday, the UN Security Council adopted a statement encouraging the three countrie ... read more

Comment using your Disqus, Facebook, Google or Twitter login.



Share this article via these popular social media networks
del.icio.usdel.icio.us DiggDigg RedditReddit GoogleGoogle

WATER WORLD
Russian Gov't allocates $60Mln to build Soyuz for tourist flights

Simultaneous presence in space surges to historic maximum of 14 people

Russian actress says 'too late' to fear ISS launch

Two Flight Engineers' stay extended in ISS

WATER WORLD
SpaceX all-civilian orbital crew completes historic mission

SpaceX Inspiration4 mission sent 4 people with minimal training into orbit

Combined tests start for Ariane 6 at Europe's Spaceport

Inspiration4 civilian mission plans splashdown Saturday evening

WATER WORLD
Justin Simon Shepherds Perseverance through first phase of Martian rock sampling

Take a 3D Spin on Mars and track NASA's Perseverance Rover

NASA's Ingenuity Helicopter Captures a Mars Rock Feature in 3D

Flying On Mars is getting harder and harder

WATER WORLD
Chinese astronauts return to Earth after 90-day mission

China prepares to launch Tianzhou-3 cargo spacecraft

Chinese astronauts return to earth after 90-day mission

Chinese astronauts complete three-month space mission

WATER WORLD
India to revise FDI policy for space sector, says ISRO chief Sivan

Adaptable optical communications to facilitate future low-earth orbit networks

SpaceX launches Starlink satellites into orbit from West Coast

China launches Zhongxing-9B satellite

WATER WORLD
Chinese game makers vow to cut effeminacy, limit underage players

Engineering researchers develop new explanation for formation of vortices in 2D superfluid

Researchers find a new way to control magnets

EPFL engineers introduce a new approach for recycling plastics

WATER WORLD
Observations in stellar factory indicates start of planet production

How planets may be seeded with the chemicals necessary for life

Planets form in organic soups with different ingredients

Antennas searching for ET threatened by wildfire

WATER WORLD
A few steps closer to Europa: spacecraft hardware makes headway

Juno joins Japan's Hisaki satellite and Keck Observatory to solve "energy crisis" on Jupiter

Hubble finds first evidence of water vapor on Ganymede

NASA Awards Launch Services Contract for the Europa Clipper Mission









The content herein, unless otherwise known to be public domain, are Copyright 1995-2024 - Space Media Network. All websites are published in Australia and are solely subject to Australian law and governed by Fair Use principals for news reporting and research purposes. AFP, UPI and IANS news wire stories are copyright Agence France-Presse, United Press International and Indo-Asia News Service. ESA news reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. All articles labeled "by Staff Writers" include reports supplied to Space Media Network by industry news wires, PR agencies, corporate press officers and the like. Such articles are individually curated and edited by Space Media Network staff on the basis of the report's information value to our industry and professional readership. Advertising does not imply endorsement, agreement or approval of any opinions, statements or information provided by Space Media Network on any Web page published or hosted by Space Media Network. General Data Protection Regulation (GDPR) Statement Our advertisers use various cookies and the like to deliver the best ad banner available at one time. All network advertising suppliers have GDPR policies (Legitimate Interest) that conform with EU regulations for data collection. By using our websites you consent to cookie based advertising. If you do not agree with this then you must stop using the websites from May 25, 2018. Privacy Statement. Additional information can be found here at About Us.